Blaine Crossing would add 614 residential units at Hailey's south end, according to its August 2026 application. Five hundred of them are rental apartments. Of the 114 single-family homes and townhomes, the developer's program lists 75% for owners and 25% as rentals. That works out to about 85 homes a household could buy, and the developer's own phasing table puts most of them after 2036.
For someone comparing Hailey with Ketchum or Sun Valley this fall, that means the project's headline unit count says very little about how many homes will be for sale in Hailey over the next several years.
What the Application Actually Proposes
The proposal covers 108.8 acres of Flying Hat Ranch, on the east side of state Highway 75 between Hailey and Bellevue. Boise-based Oppenheimer Development Corp. submitted a letter of intent on behalf of the landowners, and Seattle-based architecture firm GGLO did the design work. The Idaho Mountain Express reported that the plan pairs housing with light-industrial, commercial, and hotel uses. In the developer's project description, those uses break down as 280,000 square feet of limited industrial, 25,000 square feet of service-oriented commercial, 10,000 square feet of retail, and a 100-key hotel.
Here is the residential program as the developer submitted it to the city:
| Housing type | Quantity | Average size | Proposed occupancy |
|---|---|---|---|
| Single-family | 68 homes | 2,400 sq. ft. | 75% owner, 25% rental |
| Townhomes | 46 | 1,600 sq. ft. | 75% owner, 25% rental |
| Apartments | 500 | 750 sq. ft. | 100% rental |
| Total | 614 units |
Even that mix isn't fixed. A preliminary water report that Brockway Engineering prepared for the application, dated September 9, 2026, assumes 80 single-family homes and 450 multifamily units. The memo says its demand estimates may change as plans are finalized. Two documents in the same application describe different neighborhoods, which tells you how early in the process this is.
Rentals First, Single-Family Homes Last
The project description splits the buildout into three five-year phases. The order matters more than the total.
- Phase 1, 2027 to 2031: 450 apartments, 200,000 square feet of light industrial, the Blaine County Recreation District athletic fields with a restroom and concessions building, and a pump station. No single-family homes or townhomes.
- Phase 2, 2032 to 2036: 50 apartments, 30 townhomes, 25,000 square feet of commercial space, 80,000 square feet of light industrial, and the 100-key hotel.
- Phase 3, 2037 to 2041: the remaining 16 townhomes and all 68 single-family homes.
Apply the 75% owner share to each phase. On the developer's schedule, roughly 22 for-sale townhomes would arrive sometime in Phase 2, between 2032 and 2036, and the other 60 or so owner-occupied homes would come in Phase 3. The first single-family homes are scheduled for 2037 at the earliest. Skip Oppenheimer, the developer's chairman and CEO, told the Idaho Mountain Express at a public open house that Blaine Crossing could be a 15-year project.
So most of the early impact would fall on Hailey's rental market and on the valley's commercial and industrial space. The ownership market would see little of it. That reading assumes the project is approved and built on schedule, and neither has happened yet.
Where the Application Stands This Month
On July 13, 2026, Hailey's City Council voted unanimously to approve an annexation review agreement. That agreement sets the terms for reviewing the application. It does not approve annexation or construction. The council based its vote on three questions: whether the owners consented, whether the land borders the city, and whether the area is in Hailey's comprehensive plan. The agreement also requires the developer to pay the city $35,000 to cover staff and consultant review time, according to the Mountain Express.
Hailey's active land use applications page shows the formal application, a completeness checklist dated September 14, 2026, and public comments received through September 30. According to a summary of Bellevue's October 5 Planning and Zoning meeting, Bellevue staff said Hailey's first hearing was scheduled for November 2. Hailey had not posted that hearing on its own agenda pages as of early October, so treat the date as reported, not confirmed.
Under the Hailey municipal code, the Planning and Zoning Commission holds a public hearing and makes a recommendation. The City Council then holds its own hearing and makes findings, including on fiscal impacts. It can approve the annexation, add conditions, or deny it. It can also require an annexation agreement, fees, improvements, or security. The application has to include a traffic study, a floodplain study, an avalanche study, a wildlife study, a description of water rights, and a fiscal impact analysis.
There is a second track. The development team also plans to ask Bellevue to annex part of the ranch for related uses, including about 25 acres of recreation fields that the Blaine County Recreation District would own and operate. The Mountain Express reported that acreage as about 143 acres in July and as more than 118 acres in October.
Hailey Has Run This Experiment Before
The best guide to how Blaine Crossing might unfold is Quigley Farm, at the mouth of Quigley Canyon on Hailey's east side. It was also an annexation, and it was also planned as a mixed neighborhood. Its timeline as reported by the Mountain Express:
- July 2017: Hailey City Council unanimously approves the Quigley Farm annexation.
- Early 2018: The land is annexed into the city.
- March 2018: A preliminary large-block plat for phase one is approved, which allows infrastructure work to begin.
- June 2018: The developer says he expects to break ground within two months and that 13 of 27 phase-one lots are spoken for.
- Summer 2018: The team stakes out property boundaries and roads for phase one, but no construction follows.
- 2019: The Mountain Express reports that no visible infrastructure has been installed.
- January 2022: Nine homes are under construction and all 28 first-phase residential lots are spoken for, per the Mountain Express. The full plan calls for 176 housing units.
It took about four years to go from annexation to nine houses under construction. Part of the delay is built into the process. Roads and other infrastructure have to go in before lots can be sold. In 2019, Hailey's Community Development Director said Quigley's developers were current on a $232,821 annexation fee payment, and that another $347,517 was due before the smaller final plats in phase one could be completed and lots sold. Construction costs played a part too. In 2022, developer Dave Hennessy discussed peak lumber prices.
The same 2019 article covered a second annexation, the 27-unit Colorado Gulch Preserve on Broadford Road. Its annexation agreement was finalized in August 2018. A year later the roads and infrastructure were done, few lots had sold, and one house was under construction.
Blaine Crossing is several times larger than either project, and its Phase 1 start of 2027 assumes an annexation decision that hasn't been made. If the project follows Quigley's pace, Phase 1 could run into the early 2030s. That would push the townhomes and single-family homes later still.
The Smaller Projects That May Arrive First
The for-sale homes most likely to reach Hailey's market in the near term are small. They come from mission-driven builders, not from Flying Hat Ranch.
- Sawmill Cottages. The Wood River Land Trust and LEAP Housing have proposed homes on a 15-acre parcel between Bullion Street and Bow Bridge, with 7 homes on one parcel, 25 on another, and a 9.82-acre greenbelt kept as open space. The Land Trust describes them as workforce housing with appreciation caps and no income caps. On April 13, 2026, the council voted 2 to 1, with one abstention, to advance the letter of intent and review process. That vote did not approve the annexation itself.
- St. Luke's employee townhomes. The St. Luke's Wood River Foundation proposed nine townhomes at 1600 Appaloosa Road, ranging from 638 to 1,274 square feet. They are planned as rentals, with possible sales to employees later, the Mountain Express reported when Planning and Zoning advanced the plan. According to the April 13, 2026 council minutes, the City Council then approved the preliminary plat.
- Accessory dwelling units. Hailey has a pending code amendment, based on state law, that would change ADU rules on size, design review, occupancy, and parking. The city's register still lists it as a pending text amendment.
None of these will change the market much. Sawmill Cottages has deed-based appreciation caps, so its homes would trade under different rules than a typical resale.
What Else Is Unsettled
Several questions raised in public comment will shape both whether Blaine Crossing is approved and how it is built. Blaine County Commissioner Lindsay Mollineaux questioned whether the hotel and light-industrial uses fit Hailey's comprehensive plan. Residents of Hailey and Bellevue raised traffic on Highway 75, the loss of farmland, and possible effects on the Big Wood River and Silver Creek, the Mountain Express reported. Doug Oppenheimer, the developer's president, has said the team would not allow the project to harm local waterways.
The highway is a timing issue of its own. The Idaho Transportation Department plans to widen Highway 75 to four lanes from Birch Street in Bellevue to Fox Acres Drive in Hailey. An ITD spokeswoman told the Mountain Express that no date has been set for that stretch, and that funding so far covers only design work from Birch Street to Spruce Street in Bellevue.
Questions Buyers Ask About Blaine Crossing
What has Hailey approved so far?
As of mid-October 2026, Hailey has approved only an agreement that governs how the application will be reviewed. Planning and Zoning hearings and City Council hearings come next, and the council can approve, condition, or deny the annexation.
When would single-family homes be built?
The developer's submitted phasing puts all 68 single-family homes in Phase 3, from 2037 to 2041. That schedule assumes Phase 1 starts in 2027.
Will the apartments be for sale?
The application designates all 500 apartments as 100% rental.
Does the project change anything for a Hailey home purchased now?
It mainly affects the long-term picture at Hailey's south end: traffic patterns, nearby commercial uses, and new recreation fields. On the developer's own schedule, very little of it would be for-sale housing that competes with existing Hailey homes in the next several years.
If you're weighing a Hailey purchase while Blaine Crossing moves through review, Stevenson Real Estate Group can go through the hearing calendar with you as it develops and show you how the south-end proposals compare with what is listed in Hailey today.
This article is general information, not legal, tax or financial advice. Consult a qualified professional about your situation.