At a May 21 meeting, an Idaho Transportation Department project manager met with the Blaine County commissioners and walked them through the plan for Buttercup Road. The highway would move away from the Zinc Spur subdivision, which made the existing turn too tight, so Buttercup would end in a cul-de-sac. "We know a lot of people like to park there and access the trails," he said, according to the Idaho Mountain Express. One commissioner noted that Buttercup also works as a parallel emergency route and a way off the highway. Another asked whether the northern connection could be realigned and kept.
The plan for that corner has changed since. ITD's current project page no longer mentions a cul-de-sac. It says the Buttercup Road connection to SH-75 will be "modified." In Mid Valley, the stretch between Hailey and Ketchum, that kind of change at a single intersection is the useful way to read the whole project. The state's plan for Highway 75 handles each turnoff differently. Its walking and transit pieces are also on a faster schedule than the widening. For anyone comparing homes here over the next few years, which turnoff a house uses matters more than the subdivision name on the listing.
The Plan Has Already Changed Once
The project is called "SH-75: Bellevue to Broadway Run." It would widen the highway to five lanes, two each way with a center turn lane, from Spruce Way in north Hailey to Greenhorn Road and East Fork Road. It would also rebuild several intersections and add underpasses and bus stops. ITD says the design is meant to carry projected traffic in 2050, and that peak-hour congestion in the corridor comes mainly from commuters traveling within it.
In that same report, the Mountain Express described a $70 million first phase. It covered 5.5 miles from McKercher Boulevard to East Fork Road, did not include land costs, and could have started as early as fall 2025. That fall has come and gone. ITD's own timeline now says final design is being completed in 2025 and 2026, and that construction may begin as early as 2027. In June 2026, the ITD Board moved $200,000 of design money into the current fiscal year, with construction placed in fiscal year 2027 of the draft Idaho Transportation Investment Program. The project page still lists the project as being in planning and design.
The biggest design change is at Deer Creek.
Buttercup and Deer Creek
The earlier plan would have extended Deer Creek Road east through Peregrine Ranch to meet Buttercup Road. It also called for a traffic signal, a pedestrian underpass and a bus stop at Deer Creek. According to the Express, two commissioners worried that a Deer Creek light would back up traffic from Hailey.
The current design drops the extension, the underpass and the Deer Creek bus pullout. ITD says further engineering and traffic analysis found them "not warranted at this time," and that it will look at the extension again once development occurs in the area. Deer Creek will instead meet the highway at a T intersection with two lanes in each direction. There will be a northbound left-turn lane onto Deer Creek, and the center lane will give drivers turning left out of Deer Creek a refuge before merging.
For a buyer, this is the part of Mid Valley where the most remains to be decided. ITD will reconsider the Deer Creek extension once the area develops, and the final design of the Buttercup connection has not been published.
Ohio Gulch and Starweather
At Ohio Gulch Road, the plan adds the most. ITD would modify the existing signal and add bus pullouts on both sides of the highway. It would also build a park-and-ride on the east side at Ohio Gulch Road and Starweather Drive, with a pedestrian underpass at the same corner. The southbound bus pullout would move to the northwest corner of Starweather Drive, and the Hiawatha Canal crossing would be rebuilt and lengthened. ITD says the park-and-ride site will also hold a future bus charging station. Pathways would connect the new underpasses to the trail that runs from Bellevue to Ketchum.
For homes on either side of this intersection, that is a real change to daily access. North of Hailey's Main Street, the Mountain Rides Valley Route timetable lists two highway stops before Ketchum: Hwy 75 & East Fork and Meadows/Broadway Run. Starweather and Gimlet are not on it.
The earlier plan also shifted the highway east between Meadow Drive and the old Gimlet Railroad Bridge, where ITD owns a 240-foot strip of right-of-way. The Express reported that this would bring the shoulder closer to the Valley Club and Heatherlands, which sit much farther back from the highway than Zinc Spur and other subdivisions on the west side. ITD says existing berms along the highway will be preserved or replaced if construction significantly affects them.
The corridor's elk are part of this stretch too. ITD describes them as a resident herd rather than a migrating one and says no wildlife overpass is planned. During construction, it plans to replant roadsides with low-growing grasses and remove irrigation so the shoulders attract fewer animals.
East Fork, Greenhorn and the River Bridge
North of Ohio Gulch, the center turn lane ends between Ohio Gulch Road and the Big Wood River. From River Bend Lane to Greenhorn Road and East Fork Road, the plan calls for five lanes everywhere except across the Big Wood River bridge. It also adds an emergency signal at Fire Station Lane.
The southbound East Fork bus stop would move from the south side of the intersection to the north side. ITD says this lets passengers get off more safely and makes it easier for buses to pull back into traffic. On weekdays, northbound buses run there from 6:29 a.m. to 9:59 p.m. and southbound buses from 7:21 a.m. to 10:51 p.m. They come about every half hour at commute times, with longer gaps midday and late in the evening. On weekends they come about hourly. All Mountain Rides routes are free. For buyers looking at East Fork or Greenhorn, the planned changes at this turnoff are modest.
Broadway Run
At Broadway Run, the north end of the project and the site of the Meadows/Broadway Run bus stop, ITD plans a pedestrian underpass and bus pullouts on both sides of the highway. This is one of the two underpasses ITD lists for Mid Valley. Ohio Gulch and Starweather is the other.
Two Projects, Two Schedules
Mid Valley buyers can't time construction by one date, because the work has been split in two. In board minutes included in its May 20, 2026 meeting packet, Mountain Rides recorded that ITD had separated the transit work from the larger Highway 75 project. Funding was still in place for the underpasses and bus stop improvements through a federal RAISE grant. ITD planned to finish shovel-ready plans before a September 30 deadline to keep that grant, and construction could begin as early as summer 2027. ITD describes the grant as $12.4 million, secured jointly with Mountain Rides. A September 1, 2026 design memo in the ITD Board packet set aside separate design work for pedestrian improvements at Ohio Gulch, East Fork and Broadway Run.
The widening is on the slower schedule. The ITD Board's recommended FY27–33 program says future development and construction depend on state and federal money becoming available. In practice, a house near Ohio Gulch or Broadway Run could get an underpass and a better bus stop before the road in front of it is widened. A house that relies on Buttercup or Deer Creek is waiting on the part of the plan that is still changing.
| Turnoff | Today | In ITD's current design |
|---|---|---|
| Buttercup Road | Connects to SH-75 | Connection "modified" |
| Deer Creek Road | Connects to SH-75 | T intersection with turn lanes; extension, underpass and bus pullout dropped |
| Ohio Gulch / Starweather | Signal; not a named Valley Route stop | Signal modified, bus pullouts both sides, park-and-ride, underpass |
| Greenhorn / East Fork | Valley Route stop, about half-hourly at weekday commute times | Five lanes except the river bridge; southbound stop moves north of the intersection |
| Broadway Run | Meadows/Broadway Run Valley Route stop | Underpass and bus pullouts both sides |
The Corridor This Winter
The paved trail that the planned underpasses would connect to is the Wood River Trail, which BCRD describes as a free, 32-kilometer path linking Bellevue, Hailey, Ketchum and Sun Valley. In winter, BCRD grooms it for Nordic skiing, usually every other day. BCRD's November 20 report said the week's storms had brought enough snow to start grooming at Galena Lodge and on the North Harriman, and that crews had begun packing the Quigley trails in Hailey. A BCRD adult Nordic season pass for 2026–27 is $285 plus tax through the preseason sale ending November 29, and $340 after that.
Mid Valley commuters heading north should still expect some work in Ketchum. ITD's separate SH-75 project from Elkhorn Road to River Street is in construction, with intermittent lane shifts, flagging and closures through early December and a 25 mph limit in the work zone. For trips to the airport, the Valley Route no longer stops at Friedman Memorial. Mountain Rides now runs a free airport shuttle seven days a week.
For a sense of Mid Valley beyond its highway, our earlier look at the garden tour and bike path that hold this stretch together covers the other side of living here.
If you are weighing a home in Gimlet, Starweather, the Valley Club or East Fork, Stevenson Real Estate Group can go through ITD's segment plans for the turnoff that home depends on, so you know what is planned at that corner before you make an offer. Explore Sun Valley Homes.